UPCL Net Metering Guide for Industrial Consumers 2026
Guides

UPCL Net Metering Guide for Industrial Consumers 2026

Sun Wave Technologies16 November 202613 min read

How does UPCL net metering work for industrial consumers in 2026?

Uttarakhand Power Corporation Limited (UPCL) runs rooftop-solar net metering on a net-energy settlement basis: you install solar up to 100% of your sanctioned load or contract demand (capped at 1 MW per premises), every unit you self-consume replaces grid power at your retail tariff, and in each billing period any net import is billed at the normal tariff while any net surplus is paid at ₹2.00 per kWh. For an LT industrial consumer, that retail tariff is ₹5.75 per kVAh in FY 2026-27; for an HT factory it is ₹6.85 per kVAh (up to 50% load factor). Applications go through UPCL's solar rooftop portal (usrp.upcl.org) or the NOC form addressed to the Chief Engineer (Solar Cell) in Dehradun, and UPCL must complete connection agreement, metering and commissioning within 15 days of receiving your installation certificate.

TL;DR: capacity up to 100% of sanctioned load, max 1 MW | net-energy settlement each billing cycle | surplus paid ₹2.00/kWh | LT industry ₹5.75/kVAh, HT ₹6.85/₹6.60 per kVAh in FY 2026-27 | feasibility study required above 10 kW | commissioning within 15 days of installation certificate | apply via usrp.upcl.org.

Last verified: 16 November 2026

Uttarakhand is the last major North-Indian discom most industrial buyers have not read up on, and the economics are attractive: UPCL's FY 2026-27 tariff order raised industrial energy charges for some consumers (the LT rate now carries a time-of-day structure), while the rules let you offset that power unit-for-unit at retail value. This guide covers the capacity limits, the tariffs solar actually offsets, the ₹2/kWh surplus rate, the application process, the charges you pay, and a worked example for a Rudrapur-size factory. For the broader picture, see our industrial solar guide for Rudrapur and Haridwar.

Contents

What the UERC rules allow: capacity, group net metering, captive plants

The Uttarakhand Electricity Regulatory Commission (UERC) governs grid-interactive rooftop and small solar plants (GRPV/GSPV) through its regulations and generic-tariff orders (UERC regulations):

RuleProvision
Maximum capacityUp to 100% of the consumer's sanctioned load or contract demand, subject to a ceiling of 1 MW per premises
Domestic consumersCapacity allowed irrespective of sanctioned load (still capped at 1 MW per premises)
Transformer capCumulative GRPV/GSPV capacity on a single transformer cannot exceed that transformer's capacity
Net settlementNet-energy basis at the end of each billing period
Export paymentLower of the UERC generic tariff or the rate discovered through tariff-based bidding
Small systems (up to 10 kW)Application deemed accepted without a technical feasibility study; load-enhancement charges and security deposit for the enhanced load still apply
System strengtheningUPCL facilitates and bears capex for system strengthening/augmentation up to the interconnection point from the nearest substation
Monthly minimum chargesProsumers are exempt from monthly minimum / minimum consumption guarantee charges equivalent to the solar plant capacity
Open accessNo open access charges or surcharges on captive use of the plant's own power

Two provisions from the Uttarakhand State Solar Policy, 2023 matter to C&I buyers: group net metering is allowed for all commercial and industrial rooftop installations, and behind-the-meter captive systems with no grid export face no capacity restriction (they remain subject to Chief Electrical Inspector inspection and UREDA registration). The policy also sets a state target of 750 MW of solar from C&I consumers and provides that urban industrial and commercial establishments with a connected load of 100 kW or contract demand of 120 kVA and above are to meet at least 20% of annual energy needs from renewable sources — a policy provision, so treat the compliance mechanism as notified when you plan a larger plant.

What solar offsets: UPCL FY 2026-27 industrial tariffs

Solar only saves money at the tariff it replaces. The UERC tariff order for FY 2026-27 (effective 1 April 2026) kept UPCL's rates unchanged from FY 2025-26 while restructuring the load-factor slabs and adding a solar-hours rebate (UERC press note, 31 March 2026; UPCL tariff order):

CategoryFixed/demand chargeEnergy charge
RTS-5 LT industry, contracted load up to 75 kW₹185 per kVA of contracted load₹5.75 per kVAh (normal hours)
RTS-5 HT industry, above 88 kVA/75 kW, up to 1,000 kVA₹410 per kVA of billable demand₹6.85 per kVAh (load factor up to 50%), ₹6.60 (above 50%)
RTS-5 HT industry, above 1,000 kVA₹480 per kVA of billable demand₹6.85 / ₹6.60 per kVAh (same load-factor slabs)
Non-domestic (commercial) above 25 kW₹115 per kVA₹7.80 per kVAh

Time-of-day rates apply to LT industry above 25 kW and to all HT industry: for LT, normal hours run at ₹5.75 per kVAh, peak hours at ₹7.48, and solar hours (9 a.m. to 5 p.m.) at ₹4.46 — a 22.5% solar-hours rebate the Commission introduced in place of the earlier off-peak night rebate. HT solar-hours rates are ₹5.31 (load factor up to 50%) and ₹5.12 (above 50%), and peak-hour consumption attracts a surcharge equal to 30% of the normal tariff.

What this means for solar economics: units your panels make during the 9 a.m.-5 p.m. window displace grid power you would otherwise buy at the solar-hours rate (₹4.46 LT), while the grid power you draw in peak evening hours costs ₹7.48. Self-consumption of solar therefore offsets a blend of ToD rates — for a two-shift factory the blended avoided cost typically lands between the solar and normal rates, around ₹5-6 per unit on an LT connection and ₹6-7 on HT. Read our industrial electricity bill guide to pull the right numbers off your own bill.

Surplus export: the ₹2.00 per kWh rate

If your plant exports more than it imports over a billing period, UPCL pays for the net surplus at the UERC generic tariff for GRPV/GSPV plants: ₹2.00 per kWh for plants commissioned in FY 2025-26 (UERC order, 20 August 2025). In its April 2026 review, the Commission proposed keeping the rate at ₹2.00 per kWh for plants commissioned in FY 2026-27 (UERC review order, 7 April 2026); UPCL's implementing letter for FY 2025-26 onward plants (Letter no. 1197, February 2026) is on the UPCL website. The rate applies irrespective of any subsidy received and remains fixed for the plant's tariff period once commissioned.

The practical takeaway: ₹2 per kWh is far below the ₹5.75-6.85 you save by self-consuming, so size the plant to your daytime load, not to your sanctioned-load ceiling. A 50 kW plant on a 200-unit-a-day load is worth more than a 100 kW plant exporting half its generation.

How to apply: NOC and the UPCL solar rooftop portal

UPCL processes rooftop solar applications through the USRTPV online portal (usrp.upcl.org), where the consumer submits the application and UPCL reviews and approves it; the portal hosts stepwise user manuals for both sides. Alternatively — and as the form followed for many industrial connections — the applicant files a No Objection Certificate (NOC) request for grid connectivity and net metering with the Chief Engineer (Solar Cell), UPCL, V.C.V. Gabar Singh Urja Bhawan, Dehradun, in two copies (UPCL NOC application form, October 2026).

StepWhat happens
1. ApplicationSubmit via usrp.upcl.org or the NOC form with: latest electricity bill, photo ID, GST registration certificate (if applicable), single-line diagram (SLD), site/layout plan, authorisation letter, and a joint notarised affidavit on ₹10 stamp paper signed by the consumer and the selected vendor
2. FeasibilitySystems up to 10 kW are deemed accepted without a feasibility study; above 10 kW, UPCL conducts a technical feasibility study before approval
3. InstallationInstall the plant after approval; record the vendor, capacity and expected installation date in the application
4. Inspection and meteringSubmit the installation certificate and the meter sealing certificate issued by UPCL after grid connectivity
5. CommissioningUPCL completes the connection agreement, meter installation and commissioning within 15 days of the installation certificate
6. BillingNet-energy settlement applies from the first billing cycle after commissioning

The NOC form also commits the consumer to bear the cost of the meter, meter testing, switchgear, protection arrangements and grid synchronisation, and any augmentation of UPCL's network for evacuation of the solar power (which UPCL may carry out if the consumer deposits the cost plus supervision charges). Connectivity/interconnection charges apply as decided by UERC. Failing to submit the meter sealing certificate gives UPCL the right to disconnect the plant from the grid — keep that paperwork tight.

Charges, caps and common pitfalls

  • The export rate is not the value of solar. ₹2/kWh versus ₹5.75-6.85/kVAh retail means every unit exported earns about a quarter to a third of a unit self-consumed. Design for self-consumption first.
  • Demand charges do not fall with solar. Fixed/demand charges (₹185/kVA LT, ₹410-480/kVA HT) are billed on contracted load or billable demand regardless of generation — solar offsets energy charges only.
  • Solar-hours pricing cuts both ways. The 22.5% solar-hours rebate makes daytime grid power cheaper (₹4.46/kVAh LT), which slightly trims the value of each self-consumed solar unit for LT consumers above 25 kW; peak-hour drawal at ₹7.48 is what a battery or load-shifting strategy can attack next (see our solar plus BESS arbitrage guide).
  • Respect the transformer cap. If your feeder transformer is already loaded with other prosumers, feasibility may cap what you can connect.
  • 10 kW is the feasibility threshold. At up to 10 kW the application is deemed accepted; from just above 10 kW a feasibility study and its timeline apply.
  • Keep the meter sealing certificate on file — it is the paperwork UPCL's NOC conditions make mandatory.

Worked example: 100 kW rooftop for an Uttarakhand factory

Assumptions: an HT industrial consumer in Rudrapur (above 88 kVA contract demand), 100 kW rooftop plant, specific yield 1,450 kWh per kW per year, 90% self-consumption in the daytime load. Benchmark cost from Sun Wave Technologies' published C&I reference rate of ₹23,000/kW ex-GST at 100 kW — about ₹23 lakh ex-GST, final price after site survey (100 kW cost guide).

ItemValueWorking
Annual generation1.45 lakh units100 kW x 1,450 kWh/kW
Self-consumed (90%)about 1.30 lakh units
Savings from self-consumptionabout ₹8.9 lakh1.30 lakh x ₹6.85/kVAh (HT, load factor up to 50%)
Export (10%)14,500 units
Export creditabout ₹29,00014,500 x ₹2.00/kWh
Total year-1 benefitabout ₹9.2 lakh
Simple paybackabout 2.5 years₹23 lakh over ₹9.2 lakh annual benefit
Payback with 40% accelerated depreciationabout 2.2-2.3 years~₹2.3 lakh year-1 tax shield at a 25% rate; effective investment ~₹20.7 lakh

Generation figures follow our units per kW guide for North Indian cities; the depreciation mechanics are in the accelerated depreciation guide. These are planning figures — your tariff slab, load factor and tax position move the result. If your consumption is larger than a rooftop can serve, group captive solar and open access are the next levers, and UERC's captive-verification framework for Uttarakhand consumers is covered in our UPERC captive verification guide. To see Sun Wave Technologies' C&I rooftop offer and reference pricing, start at the Faridabad industrial solar service page.

Frequently Asked Questions

What is the maximum solar capacity I can install under UPCL net metering?

Up to 100% of your sanctioned load or contract demand, subject to a ceiling of 1 MW per premises, and the cumulative capacity on your feeder transformer cannot exceed that transformer's rating. Domestic consumers can install irrespective of sanctioned load, still capped at 1 MW per premises.

How much does UPCL pay for surplus solar export?

₹2.00 per kWh at the UERC generic tariff for net-metered GRPV/GSPV plants commissioned in FY 2025-26, and the Commission has proposed keeping the same rate for FY 2026-27. The rate applies irrespective of any subsidy received and is fixed for the plant once commissioned.

Is net metering available for LT industrial consumers in Uttarakhand?

Yes. UPCL's LT industrial category covers contracted loads up to 75 kW, and rooftop solar on an LT connection settles on the net-energy basis described above. LT consumers above 25 kW fall under time-of-day billing, with solar hours priced at ₹4.46 per kVAh in FY 2026-27.

How do I apply for net metering with UPCL?

Apply through the USRTPV portal at usrp.upcl.org, or file the NOC application (two copies) with the Chief Engineer (Solar Cell), UPCL, Dehradun, enclosing the latest bill, photo ID, GST certificate where applicable, single-line diagram, site plan, authorisation letter and a joint notarised affidavit on ₹10 stamp paper. Systems up to 10 kW skip the feasibility study; above that, UPCL runs a technical feasibility study before approval.

How long does UPCL take to commission a rooftop solar plant?

After you submit the installation certificate following installation, UPCL must complete the connection agreement, meter installation and successful commissioning within 15 days. The meter sealing certificate from UPCL is a mandatory part of the paperwork.

Does a rooftop solar plant reduce my demand charges in Uttarakhand?

No. Fixed and demand charges (₹185 per kVA on LT, ₹410-480 per kVA on HT in FY 2026-27) are billed on contracted load or billable demand and are unaffected by generation. Solar offsets the energy charge — ₹5.75 per kVAh on LT industry and ₹6.85/₹6.60 per kVAh on HT — which is where the savings come from.

Is group net metering allowed in Uttarakhand for commercial and industrial consumers?

Yes. The Uttarakhand State Solar Policy, 2023 allows group net metering for all commercial and industrial rooftop solar installations, and places no capacity restriction on behind-the-meter captive systems that do not export to the grid (these remain subject to Chief Electrical Inspector inspection and UREDA registration).