NPCL open access solar charges for FY 2026-27: what changed
UPERC's NPCL tariff order of 2 July 2026 (Petition No. 2330 of 2025) raises NPCL's average wheeling charge to ₹1.03/kWh for FY 2026-27, from ₹0.78/kWh in FY 2025-26, keeps additional surcharge at zero, and sets voltage-wise CSS from ₹0.36 to ₹1.46/kWh. For an HV-2 industrial consumer at 11 kV the CSS stays at ₹0.57/kWh, while HV-2 supply between 11 kV and 66 kV falls from ₹0.59 to ₹0.51/kWh. Embedded open access customers already paying demand charges need not pay NPCL wheeling.
TL;DR: For NPCL's licensed area in FY 2026-27: wheeling ₹1.03/kWh (unless the embedded-customer proviso applies), CSS ₹0.57/kWh for HV-2 at 11 kV, additional surcharge ₹0, plus UPPTCL transmission of ₹0.3075/kWh. These figures apply to NPCL only, not to the other Uttar Pradesh DISCOMs, whose charges are on our UP open access charges page.
Last verified: 27 October 2026. We read the NPCL order and the UPPCL state DISCOM order of the same date as published on the UPERC site; the UPPTCL transmission figure is taken from the UPPCL order's recital of the UPPTCL order. This page replaces the FY 2025-26 figures that were here earlier; the URL keeps its original FY 2025-26 slug.
In this guide:
- What changed from FY 2025-26
- Master charges table
- Wheeling and the demand-charge proviso
- Cross-subsidy surcharge
- Additional surcharge (zero)
- Transmission, losses and other charges
- Landed-cost worked example
- Is this page for your connection?
- Frequently Asked Questions
For fundamentals, start with the open access solar guide for India. The state-by-state view is in our solar open access charges by state comparison.
What changed from FY 2025-26
| Item | FY 2025-26 | FY 2026-27 |
|---|---|---|
| Average wheeling charge | ₹0.78/kWh | ₹1.03/kWh |
| CSS, HV-2 at 11 kV | ₹0.57/kWh | ₹0.57/kWh |
| CSS, HV-2 above 11 kV and up to 66 kV | ₹0.59/kWh | ₹0.51/kWh |
| CSS, HV-1 at 11 kV | ₹1.33/kWh | ₹1.33/kWh |
| Additional surcharge | ₹0 | ₹0 |
| Regulatory discount on NPCL tariff | 10% | 10% (continued) |
Other changes worth knowing:
- UPERC approves CSS as the lower of the newly computed value and the value in its 22 November 2025 NPCL order, so no category rose.
- NPCL's wheeling cost is now ₹451.70 crore over 4,399.84 MU of retail sales.
- UPERC's order of 17 June 2026, after APTEL remand, cut NPCL's FY 2023-24 surplus; the 10% regulatory discount was nonetheless retained for FY 2026-27. A consumer body has sought review of that order, so verify the current rate schedule before modelling.
Master charges table
| Charge | Unit | Value | Order reference |
|---|---|---|---|
| Average wheeling charge | ₹/kWh | 1.03 | UPERC NPCL order, 2 Jul 2026, Table 9-5 |
| Wheeling, embedded OA customer already paying demand charges | ₹/kWh | Nil (proviso to Regulation 39.2, MYT Regulations 2025) | Same, paragraph 9.2.11 |
| Wheeling losses | In kind | 33 kV 0.79%, 11 kV 2.58%, above 33 kV 0.09%, below 11 kV 6.97% | Same, Table 9-11 and paragraph 9.3.7 |
| CSS, HV-2 at 11 kV | ₹/kWh | 0.57 | Same, Table 9-14 |
| CSS, HV-2 above 11 kV and up to 66 kV | ₹/kWh | 0.51 | Same |
| CSS, HV-2 above 66 kV and up to 132 kV, and at 132 kV | ₹/kWh | 0.36 | Same |
| CSS, HV-1 at 11 kV | ₹/kWh | 1.33 | Same |
| CSS, HV-1 above 11 kV | ₹/kWh | 1.40 | Same |
| CSS, supply below 11 kV | ₹/kWh | 1.46 | Same |
| Additional surcharge | ₹/kWh | 0 | Same, paragraph 9.4.7 |
| Intra-state transmission tariff for open access | ₹/kWh | 0.3075 | UPPTCL tariff order 15 Apr 2026, as stated in the UPPCL tariff order of 2 Jul 2026, paragraph 10.2.1 |
| Intra-state transmission loss | In kind | 3.18% | NPCL order, Table 9-11 |
Wheeling and the demand-charge proviso
UPERC calculated NPCL's wheeling charge by dividing the approved wheeling tariff of ₹451.70 crore by 4,399.84 MU of retail sales, giving ₹1.03/kWh. Open access customers also bear wheeling losses in kind.
Two qualifications matter. First, wheeling is chargeable only when the distribution system is used. The order repeats UPERC's direction that an open access consumer connected directly to the transmission network should not be charged wheeling. Second, paragraph 9.2.11 quotes a proviso to clause 39.2 of the MYT Regulations 2025: embedded open access customers who are already liable for demand charges are not required to pay wheeling charges to the distribution licensee. "Embedded" and "liable for demand charges" are factual tests, so ask NPCL for a written computation instead of assuming either result. Deleting ₹1.03 from a model without that confirmation overstates your saving.
Cross-subsidy surcharge
CSS follows the consumer's category and supply voltage, not the voltage of the solar plant. UPERC approved the lower of its newly computed CSS and the CSS approved on 22 November 2025, which is why most categories did not move. HV-2 at 11 kV, the usual category for a manufacturing plant, stays at ₹0.57/kWh. The HV-1 non-industrial categories pay far more: ₹1.33/kWh at 11 kV and ₹1.40/kWh above it.
Qualifying captive consumption is not charged CSS under the proviso to Section 42(2) of the Electricity Act, 2003, but captive status has to be proved and maintained. Our group captive solar and 26% equity rule guide explains the tests.
Additional surcharge (zero)
NPCL did not claim an additional surcharge in its FY 2026-27 petition. It asked instead for permission to file a separate petition when migration to open access strands capacity, and cited 28 open access consumers at the end of FY 2024-25 and an expected 40 by the end of FY 2025-26. UPERC therefore approved the additional surcharge at zero (paragraph 9.4.7), while allowing NPCL to file a separate petition with a formal justification.
That makes zero a position for this order, not a guarantee. Regulation 38 of the MYT Regulations 2025 lets an additional surcharge apply only if stranding is conclusively demonstrated, caps it at the per-unit fixed cost, reduces it linearly to nothing within four years of open access being granted, and excludes open access to the extent of contract demand maintained with the licensee. We checked UPERC's tariff-order index on 27 October 2026 and found no separate NPCL additional surcharge order, but monitor it, because a petition could land at any time.
Transmission, losses and other charges
Use of the UPPTCL network attracts the intra-state transmission tariff UPERC set in April 2026 for open access users, which the UPPCL order records as ₹0.3075/kWh. The NPCL order applies 3.18% intra-state transmission loss to open access billing. Inter-state transactions add central transmission charges and losses, which the NPCL order carries at 3.58% for inter-state transmission in the CSS computation.
UPSLDC's load despatch charge for medium and long-term open access is ₹639.97 per MW per month for FY 2026-27 according to the Hindustan Times report on UPERC's April 2026 orders; we have not added it to the example. Scheduling and deviation charges, banking, reactive energy, metering and electricity duty also sit outside the example.
Landed-cost worked example: HV-2 factory at 11 kV
Assumptions (illustrative, not a quote). An HV-2 industrial consumer at 11 kV buys in-state solar at ₹3.50/kWh at the plant gate. We apply the order's 3.18% intra-state transmission loss and 2.58% distribution loss at 11 kV, so 0.9432 kWh reaches the meter per kWh injected. The avoided cost is NPCL's HV-2 energy charge at 11 kV of ₹7.10/kVAh less the 10% regulatory discount, which is ₹6.39/kVAh. The demand charge of ₹300/kVA/month stays on both sides of the comparison.
| Line (₹/kWh delivered) | Wheeling applies | Embedded proviso applies |
|---|---|---|
| Solar at plant gate | 3.50 | 3.50 |
| Loss gross-up (3.18% and 2.58%) | 0.21 | 0.21 |
| UPPTCL transmission | 0.31 | 0.31 |
| NPCL wheeling | 1.03 | 0.00 |
| CSS, HV-2 at 11 kV | 0.57 | 0.57 |
| Additional surcharge | 0.00 | 0.00 |
| Landed cost | 5.62 | 4.59 |
| NPCL energy charge avoided (net of 10% discount) | 6.39 | 6.39 |
| Saving per kWh | 0.77 | 1.80 |
If the project qualifies as captive, remove the ₹0.57 CSS and the saving rises to about ₹1.34 with wheeling or ₹2.37 with the proviso. Time-of-day rebates and surcharges of 15% change the avoided cost by hour, and the table omits SLDC, scheduling and banking, so treat it as a first screen. The point is that this is an NPCL-specific stack: the 10% regulatory discount lowers the grid cost that open access replaces. See our industrial solar in Noida guide for the on-site alternative, and our NPCL net metering note, which explains why industrial net metering is not available there. Size any plant to your daytime load with the factory solar sizing guide.
Is this page for your connection?
NPCL, or Noida Power Company Limited, is a specific distribution licensee with a defined licensed area. A postal address containing "Noida" does not prove NPCL supply, and parts of the wider region are served by PVVNL, whose order is on our UP open access charges page. Greater Noida's NIDP data centre park has its own UPERC order (Petition No. 2327 of 2025). Check the licensee on your bill. City-level guides such as industrial solar in Greater Noida must also use the actual licensee.
Frequently Asked Questions
What is NPCL's wheeling charge for open access in FY 2026-27?
UPERC approved an average wheeling charge of ₹1.03/kWh for NPCL in its order of 2 July 2026, up from ₹0.78/kWh in FY 2025-26, plus wheeling losses in kind. Embedded open access customers who already pay demand charges are not required to pay it under the MYT Regulations 2025 proviso.
What is the CSS for NPCL HV-2 industrial consumers at 11 kV?
₹0.57/kWh for FY 2026-27, unchanged from FY 2025-26. HV-2 supply above 11 kV and up to 66 kV is ₹0.51/kWh (down from ₹0.59), and HV-2 at 132 kV and above 66 kV is ₹0.36/kWh. Qualifying captive consumption is exempt.
Is there an additional surcharge for open access in Noida under NPCL?
No. UPERC approved the additional surcharge at zero in the NPCL order because NPCL did not claim one, while allowing NPCL to file a separate petition with justification. We found no such order on UPERC's tariff-order index on 27 October 2026.
Do NPCL open access customers who pay demand charges pay wheeling?
Not under paragraph 9.2.11 of the order, which quotes the MYT Regulations 2025 proviso exempting embedded open access customers already liable for demand charges. Whether you qualify depends on your connection, so obtain NPCL's written computation.
What transmission charge applies to open access in the NPCL area?
The UPPTCL intra-state transmission tariff for open access users is ₹0.3075/kWh for FY 2026-27, with 3.18% intra-state transmission loss applied to open access billing in the NPCL order. Inter-state transactions add central charges.
Are NPCL's open access charges the same as UPPCL's for the rest of Uttar Pradesh?
No. NPCL has its own order. For example, UPPCL's state DISCOM wheeling charge is ₹0.9318/kWh against NPCL's ₹1.03/kWh, and CSS tables differ. Use the order of your billing licensee.
Is open access solar cheaper than NPCL's industrial tariff?
Modestly. At a ₹3.50/kWh plant-gate price our HV-2 example lands at ₹5.62/kWh with wheeling or ₹4.59/kWh if the embedded proviso applies, against about ₹6.39/kVAh for NPCL's energy charge after its 10% discount. Captive structures save more.
Sources
- UPERC NPCL tariff order, True-up FY 2024-25, APR FY 2025-26 and ARR and Tariff FY 2026-27, Petition No. 2330 of 2025, 2 July 2026
- UPERC order for the State DISCOMs, 2 July 2026, Chapter 10 (transmission, wheeling, CSS)
- UPERC tariff-order index, checked 27 October 2026
- Hindustan Times: UPERC fixes FY27 transmission tariff and LDC charges
Ready to Go Solar?
Get a free consultation and custom quote for your industrial or commercial facility. Start saving on energy costs today.
Get Free Quote