Open Access Solar in India: Complete Guide for Industry
Open Access

Open Access Solar in India: Complete Guide for Industry

Sun Wave Technologies1 April 202610 min read

Key Takeaways

What Is Open Access Solar?

Open access solar allows industrial electricity consumers to purchase solar power from a generator located anywhere in the same state (or sometimes across states) through the existing transmission and distribution network. Unlike rooftop solar that requires panels on your building, open access solar can be generated at a remote solar farm.

Think of it as buying solar electricity the same way you buy grid electricity — through the transmission network — but at a lower cost and with green energy benefits.

Who Is Eligible for Open Access Solar?

Eligibility varies by state, but the general criteria are:

ParameterTypical Requirement
Minimum contracted demand1 MW (some states: 500 kW or 100 kW)
Connection typeHT (High Tension) — 11 kV or above
Electricity categoryIndustrial, commercial, or institutional
Payment historyNo outstanding dues with DISCOM

Key point: If your factory's connected load is below 1 MW, rooftop solar with net metering is the better option. Open access becomes advantageous for larger consumers.

Types of Open Access Solar

1. Group Captive Model (Most Popular)

In a group captive arrangement, the industrial consumer invests 26% of the equity in the solar power plant and commits to purchasing at least 51% of the electricity generated.

How it works:

  1. A solar developer builds a 5–50 MW solar plant
  2. Multiple industrial consumers invest 26% equity proportional to their power share
  3. Consumers purchase electricity at a pre-agreed PPA rate
  4. Key benefit: 100% waiver on cross-subsidy surcharge (CSS), saving ₹1–2.5/kWh

Economics:

Compared to grid tariffs of ₹8–13/kWh, that's a savings of 35–55%.

2. Third-Party Open Access

In this model, you simply purchase solar electricity from a developer without any equity investment. It's simpler but slightly more expensive due to cross-subsidy surcharge.

How it works:

  1. A solar developer generates electricity
  2. You sign a PPA to purchase a fixed quantity at an agreed rate
  3. Electricity is wheeled through the DISCOM/transmission network to your factory

Economics:

The economics are state-dependent. In high-CSS states, third-party open access may not save much. In states with lower CSS (like Gujarat, Rajasthan), it's viable.

3. Bilateral Open Access

Direct arrangement between generator and consumer, typically for very large consumers (5 MW+). Requires regulatory approvals from the State Electricity Regulatory Commission (SERC).

Comparison of Open Access Models

FactorGroup CaptiveThird-PartyBilateral
Equity investment26% requiredNoneNone
Cross-subsidy surchargeWaived (0%)Full (₹1–2.5/kWh)Full or partial
Minimum size1 MW share1 MW5 MW+
PPA flexibilityLocked with plantCan change developersHighly customizable
Setup complexityMediumLowHigh
Best forCost-conscious buyersQuick procurementVery large consumers

State-Wise Open Access Solar Economics

Haryana Open Access Solar

Rajasthan Open Access Solar

Rajasthan offers some of the best open access economics in India due to low CSS and excellent solar irradiance.

Gujarat Open Access Solar

Gujarat's low CSS makes even third-party open access viable without group captive investment.

Maharashtra Open Access Solar

Despite high CSS, Maharashtra's even higher grid tariffs make open access solar highly attractive, especially in the group captive model.

Open Access vs. Rooftop Solar: Which Is Right for You?

FactorOpen Access SolarRooftop Solar
Location of panelsOff-site (developer's land)On your rooftop
Your investment (CAPEX)26% equity (group captive) or ₹0 (PPA)Full EPC cost or ₹0 (RESCO)
Capacity limitNo limit (can procure MW-scale)Limited by roof area
Transmission charges₹0.5–1.5/kWhNone
Cross-subsidy surcharge₹0–2.5/kWhNone
Effective cost per unit₹4.5–7.0₹2.5–5.5
Maintenance responsibilityDeveloperYou (CAPEX) or developer (RESCO)
Best forLarge consumers (1 MW+) with limited roofAll sizes with adequate roof space

The best strategy for large consumers: Install maximum rooftop solar first (cheapest per unit), then supplement with open access for additional requirement.

How to Procure Open Access Solar: Step by Step

Step 1: Assess Your Eligibility and Requirement

Step 2: Find a Solar Developer

Look for developers with:

Step 3: Negotiate the PPA

Key terms to negotiate:

Step 4: Apply for Open Access Permission

Step 5: Set Up Metering and Billing

Real-World Economics: Open Access Solar Case Study

Large Manufacturer in Manesar, Haryana (3 MW demand)

Current situation:

Solution: 2 MW Group Captive Solar + 500 kW Rooftop

ComponentCapacityCost per UnitMonthly UnitsMonthly Cost
Rooftop solar500 kW₹0 (owned, post-payback)65,000₹0
Group captive OA2 MW₹5.2/kWh (all-in)5,20,000₹27 lakhs
Grid (balance)Variable₹9.2/kWh4,15,000₹38 lakhs
Total12,00,000₹65 lakhs

Monthly savings: ₹45 lakhs (41% reduction) Annual savings: ₹5.4 Crore

Challenges and Risks in Open Access Solar

Regulatory Uncertainty

State electricity regulatory commissions periodically revise open access charges. CSS and additional surcharge can increase, reducing savings. Mitigation: Long-term open access agreements typically lock in charges for the agreement period.

Banking Restrictions

Some states limit or don't allow energy banking (carrying forward excess units to the next month). This means if your consumption is lower than generation in a given period, you may lose units. Mitigation: Accurate demand forecasting and scheduling.

Deviation Charges

If the actual solar generation deviates significantly from the scheduled quantum, deviation settlement charges apply. Mitigation: Work with developers who have accurate generation forecasting capabilities.

Counter-Party Risk

In group captive, if other equity partners exit, the financial structure changes. Mitigation: Work with reputed developers and ensure the shareholder agreement has clear exit and entry provisions.

Frequently Asked Questions

What is the minimum load required for open access solar in India?

The minimum contracted demand for open access solar varies by state. In most major industrial states, it's 1 MW. However, Rajasthan allows open access for solar at 500 kW, and some states are reducing the threshold further. For factories below the open access threshold, rooftop solar with net metering is the recommended alternative.

What is the difference between group captive and third-party open access?

In group captive, you invest 26% equity in the solar plant and consume at least 51% of its output — in return, you get a 100% waiver on cross-subsidy surcharge (saving ₹1–2.5/kWh). In third-party open access, you simply buy power without equity investment but pay the full CSS. Group captive costs ₹4–6.5/kWh all-in, while third-party costs ₹5–9/kWh depending on the state.

Can I combine open access solar with rooftop solar?

Absolutely. This is the recommended approach for large consumers. Install maximum rooftop solar first (it's the cheapest at ₹2.5–3.5/kWh LCOE with no transmission charges), then procure additional solar through open access for your remaining demand. Sun Wave Technologies can design a comprehensive solution combining both rooftop EPC and open access procurement.

How much can I save with open access solar compared to grid tariff?

Savings depend on your state's grid tariff and open access charges. In the group captive model, typical savings range from 30–55% of grid tariff. In third-party model, savings range from 15–35%. For a factory consuming 10 lakh units per month at ₹9.5/kWh grid tariff, group captive open access solar can save ₹3–5 Crore per year.

Is open access solar reliable? What happens on cloudy days?

Open access solar has the same weather dependency as any solar system — generation drops during cloudy or rainy periods. The difference is that your DISCOM automatically supplies the shortfall from the grid. You pay grid tariff for the grid units and PPA rate for the solar units. Over a year, solar typically delivers 90–95% of the scheduled generation, with seasonal variations.

What are the tax benefits of group captive solar?

In a group captive arrangement, your 26% equity investment qualifies for accelerated depreciation (40% in year 1), which creates a tax shield of approximately 25–30% of your investment. Additionally, the solar PPA rate is treated as an operating expense, fully deductible from business income. The combination of tax benefits and lower electricity costs makes group captive one of the most attractive solar procurement options for profitable companies.

Ready to Go Solar?

Get a free consultation and custom quote for your industrial or commercial facility. Start saving on energy costs today.

Get Free Quote