DHBVN Solar Net Metering Guide for Industrial & Commercial Consumers (2026)
Guides

DHBVN Solar Net Metering Guide for Industrial & Commercial Consumers (2026)

Sun Wave Technologies2 July 202614 min read

TL;DR — Solar Net Metering for Haryana Industrial Consumers

Why Net Metering Matters for Haryana Industrial Buyers

For a factory owner in Faridabad, Gurugram, Sonipat, or Panipat, net metering is the financial mechanism that makes rooftop solar viable. Here's how it works:

  1. Your solar plant generates power during daylight hours — when your factory is running.
  2. Self-consumption: solar power is consumed directly by your machines, offsets grid electricity at your full retail tariff (₹7.50–9.85/kWh depending on slab and Time-of-Day).
  3. Excess export: when solar generation exceeds your instantaneous load (weekends, holidays, maintenance days), surplus flows to the DHBVN grid.
  4. Energy banking: exported units are credited to your account and offset against future consumption. The net is calculated monthly; unadjusted surplus carries forward.
  5. Annual settlement: every April, any remaining surplus is compensated at 75% of the last discovered SECI solar tariff (per HERC's 2nd Amendment 2025) — not at your retail tariff.

The bottom line: size your plant to match daytime consumption; treat export as a bonus, not the primary return driver.

Haryana's Net Metering Policy — What Makes It Exceptional

Haryana's net metering framework is among the most pro-industrial in India. Here's the regulatory landscape as of July 2026:

Capacity Limits

ParameterLimit
Maximum system size (net metering)1 MW per HT consumer
Upper limit with BESS mandate2 MW (with 25% / 2-hr battery storage)
Cap as % of sanctioned load100% of sanctioned load
Distribution transformer capacity cap30% of local DT capacity (HT connections)
Minimum for commercial buildings (50 kW+ load)3–5% of connected load (mandatory)

Battery Storage Mandate (1–2 MW)

For rooftop solar systems between 1 MW and 2 MW, HERC mandates 25% battery energy storage capable of delivering rated power for at least 2 hours. For a 1.5 MW plant, that means 375 kW / 750 kWh of BESS — adding approximately ₹45–65 lakh to the project capex. This BESS can also be leveraged for Time-of-Day arbitrage and demand-charge flattening, partially offsetting its cost. See our DG vs BESS comparison for the full analysis.

Charges and Exemptions

ChargeStatus for Rooftop Solar
Electricity dutyWaived
Wheeling chargesWaived
Cross-subsidy surchargeWaived
Transmission & distribution chargesWaived
Electricity tax & cessWaived
External Development ChargesExempt
Scrutiny fee & Infrastructure Development ChargesExempt
Monthly Minimum Charges (MMC)Abolished (replaced with fixed charges, FY26 ARR order)

Surplus Compensation and Settlement

Per HERC's 2nd Amendment (finalized December 2025, effective from the FY26-27 settlement period):

DHBVN Net Metering Application — Step-by-Step Process

The DHBVN application follows a structured 9-annexure workflow. Here's the end-to-end process, including what you need at each stage.

Pre-Application Checklist

Before starting the online application, gather:

  1. Latest electricity bill — HT consumer number, sanctioned load, contract demand
  2. Roof ownership documents — sale deed or lease agreement + landlord NOC if leased
  3. Single-line diagram (SLD) of the proposed solar system
  4. Module datasheets — ALMM-listed Tier-1 modules (Waaree, Adani, Vikram, Premier, Trina, Goldi, Tata Power Solar)
  5. Inverter datasheets — Sungrow, Huawei, or equivalent
  6. Structural stability certificate from a licensed structural engineer — confirming the roof can bear 12–15 kg/m² uniform load plus point loads
  7. Electrical contractor licence of the executing agency
  8. Company registration / GST certificate
  9. Authorized signatory details — name, designation, phone, email, board resolution
  10. Cancelled cheque or bank statement (for meter security deposit linkage)

Stage 1: Online Application Submission

Portal: esolarconn.dhbvn.org.in
Fee: ₹1,000 (non-refundable application processing fee)

  1. Register on the DHBVN Solar Net Metering portal. If you already have a DHBVN SFA account, use that.
  2. Complete Annexure-I (Application Form): system capacity, module type, inverter specifications, roof details, expected annual generation.
  3. Upload documents: property papers, SLD, structural certificate, module/inverter datasheets, electrical contractor licence.
  4. Pay ₹1,000 processing fee online.
  5. You'll receive an E-Form number — save this. It's your application reference for all tracking.

Stage 2: Acknowledgement and Initial Scrutiny (5–10 working days)

After submission, the sub-divisional officer reviews your application:

Pro tip from Sun Wave's DHBVN liaison team: The most common rejection reason is an incomplete or unprofessional single-line diagram. Submit a detailed SLD showing module strings, inverter placement, AC/DC protection, metering arrangement, and earthing. A hand-drawn sketch will be rejected.

Stage 3: Site Inspection and Verification (7–14 working days)

Once your application passes initial scrutiny:

Stage 4: Net Metering Authorisation (5–10 working days)

On successful site verification, DHBVN issues:

This is your green light — you may now begin physical installation.

Stage 5: Installation and Self-Certification

Install your rooftop solar system according to the approved SLD and specifications. After installation:

Stage 6: Net Meter Connection Agreement (Annexure-VI)

Before the bi-directional meter is installed, you must execute the Net Meter Connection Agreement (Annexure-VI) with DHBVN. Key terms:

Stage 7: Work Completion and Meter Installation (7–14 working days)

Stage 8: Synchronisation and Go-Live

Timeline Summary

StageTypical DurationCumulative
Application submission1 dayDay 1
Scrutiny & acknowledgement5–10 working daysWeek 1–2
Site inspection & verification7–14 working daysWeek 2–4
Net metering authorisation5–10 working daysWeek 3–6
Installation (EPC execution)45–60 daysWeek 10–14
Work completion & meter installation7–14 working daysWeek 12–16
Synchronisation & go-live2–5 working daysWeek 13–17

Total: approximately 90–120 days from application to grid-connected operation. Sun Wave's Faridabad-based DHBVN liaison team has consistently delivered approval timelines of 25–40 days for the pre-installation regulatory phases (Stages 1–4), compared to the 30–60 day standard.

Common Application Mistakes (and How to Avoid Them)

Mistake 1: Incomplete or Unprofessional SLD

DHBVN engineers review SLDs daily. A single-line diagram missing protection devices, earthing detail, or string configuration will bounce back. Fix: Have your EPC contractor prepare a detailed, CAD-quality SLD before submission.

Mistake 2: Structural Certificate from an Unlicensed Engineer

The structural stability certificate must come from a licensed structural engineer registered with the municipal corporation or equivalent authority. A letter from your factory maintenance supervisor won't suffice. Fix: Verify the engineer's credentials before submission.

Mistake 3: Module Not on ALMM List

DHBVN checks modules against the MNRE ALMM (Approved List of Models and Manufacturers). If your modules aren't listed, the application is rejected. Fix: Use only ALMM-listed modules. Current Tier-1 ALMM brands include Waaree, Adani Solar, Vikram Solar, Premier Energies, Trina Solar, Goldi Solar, and Tata Power Solar.

Mistake 4: Ignoring the Distribution Transformer Capacity Cap

If the cumulative solar capacity on your local distribution transformer already exceeds 30% (for HT), your application will be rejected regardless of your sanctioned load. Fix: Check transformer loading before committing to a project. Your EPC contractor should verify this during feasibility.

Mistake 5: Submitting Before Roof Readiness

If the site inspection reveals roof repairs needed, significant shadow obstructions, or inadequate electrical room — DHBVN will defer authorisation until resolved. Fix: Complete roof repairs, clear shadow sources (HVAC ducts, water tanks), and prepare the electrical room before applying.

Industrial Solar Cost Benchmarks — Haryana (2026)

With net metering in place, the economics are compelling. Here are the current industrial rooftop solar EPC costs for Haryana:

System SizeCost per WpTotal Installed CostAnnual GenerationAnnual SavingsPayback
100 kW₹38–44₹38–44 Lakh1.44–1.52 Lakh kWh₹11–13 Lakh3.5–4.0 years
250 kW₹36–42₹90–105 Lakh3.6–3.8 Lakh kWh₹27–33 Lakh3.2–3.8 years
500 kW₹35–40₹1.75–2.0 Cr7.2–7.6 Lakh kWh₹54–67 Lakh3.0–3.6 years
1 MW₹34.5–39₹3.45–3.90 Cr14.4–15.2 Lakh kWh₹1.08–1.34 Cr2.9–3.5 years
1.5 MW (with BESS)₹38–43₹5.7–6.45 Cr21.6–22.8 Lakh kWh₹1.62–2.01 Cr3.2–4.0 years

Assumptions: ALMM Tier-1 modules, Sungrow/Huawei string inverters, HDG IS-2062 structures, 1,440–1,520 kWh/kWp annual yield (Faridabad/Gurugram irradiation), DHBVN HT-I tariff ₹7.50–8.80/kWh. BESS pricing assumes 25% / 2-hour LFP at ₹50–65 Lakh per 500 kWh incremental.

For the full cost breakdown, see our solar EPC cost per MW guide.

RESCO/OPEX Option — Zero Capex Net Metering

For Haryana factory owners who prefer not to deploy capital, the RESCO/OPEX model works seamlessly with DHBVN net metering:

Sun Wave's Faridabad HQ offers CAPEX, RESCO, Open Access, and Group Captive — all four models. See our RESCO/OPEX solar model guide.

Frequently Asked Questions

What is the maximum solar capacity I can install under DHBVN net metering?

Up to 1 MW per HT consumer or 100% of your sanctioned load (whichever is lower). Between 1 MW and 2 MW, you must install 25% battery storage with a 2-hour duration. The cumulative solar capacity on your local distribution transformer must not exceed 30% for HT connections.

How much does the DHBVN net metering application cost?

The application processing fee is ₹1,000 (non-refundable). The bi-directional meter costs ₹15,000–25,000 (borne by consumer). There are no other DHBVN fees for net metering — remarkably, Haryana waives electricity duty, wheeling charges, cross-subsidy surcharge, and T&D charges for rooftop solar.

How long does DHBVN net metering approval take?

The pre-installation regulatory process (application through authorisation) typically takes 30–60 days. Sun Wave's DHBVN liaison team consistently achieves 25–40 days. Full go-live (including installation) is approximately 90–120 days from application.

What happens to my unused solar credits at year-end?

Per the HERC 2nd Amendment (2025), surplus energy credits carry forward within the April–March financial year. At each April reset, remaining surplus is compensated at 75% of the last discovered SECI solar tariff — not at your retail tariff. The old 90% annual generation cap has been eliminated.

Can I install solar on a leased factory premises?

Yes, with a No-Objection Certificate (NOC) from the landlord. The net metering connection is registered in the tenant's name if the lease term covers the solar plant's economic life. The landlord NOC must be notarised and submitted with the application.

Are commercial buildings required to install solar in Haryana?

Yes. All commercial complexes, offices, and malls with a connected load of 50 kW and above must install solar capacity equal to 3–5% of their connected load (mandatory under Haryana's solar policy). This applies to both existing and new buildings.

Does Haryana offer any additional incentives beyond net metering?

Beyond the total waiver of electricity duty, wheeling, cross-subsidy, and T&D charges — Haryana also exempts External Development Charges, Scrutiny Fee, and Infrastructure Development Charges for the operational period of the solar plant. For the national accelerated depreciation benefit (40% Year 1), see our solar accelerated depreciation guide.

What if my rooftop solar generation exceeds my sanctioned load?

Your system capacity cannot exceed 100% of your sanctioned load. If your generation momentarily exceeds your instantaneous consumption, the surplus is exported and credited under net metering. But you cannot install a system larger than your sanctioned load — this is a hard regulatory cap.

Can I combine rooftop net metering with open access solar?

Yes — many large industrial consumers use a hybrid approach: 1 MW rooftop under DHBVN net metering for captive consumption plus additional capacity through group captive open access from Rajasthan or UP solar parks. See our open access solar India guide and group captive solar guide.

Why choose Sun Wave Technologies for DHBVN net metering?

Sun Wave's Faridabad headquarters gives you direct, local DHBVN liaison capability: same-day site visits, established relationships with sub-divisional officers, and the shortest net metering approval timelines in NCR (25–40 days vs 30–60 standard). We handle the entire application process — you focus on your factory. 50+ MW commissioned across Haryana, Rajasthan, UP, and Gujarat industrial clients.

Sources


Sun Wave Technologies — Industrial & commercial solar EPC. Faridabad HQ. 50+ MW commissioned across Delhi-NCR, Haryana, Rajasthan, UP, and Gujarat.

Ready to Go Solar?

Get a free consultation and custom quote for your industrial or commercial facility. Start saving on energy costs today.

Get Free Quote